Free PE Civil — Transportation practice problems
Ten real questions from our PE Civil: Transportation bank — one from each knowledge area, with the same exam-realistic figures and fully worked solutions our members get. No signup, no email. Try each one first, then reveal the solution.
- 1mediumA. Clear zone, slopes & barrier length-of-needOn the outside of a 1,500-ft-radius curve (design speed 60 mph), the tangent clear-zone value from the RSDG table is ft. The RSDG curve-adjustment factor for this radius and speed is . The adjusted clear-zone distance on the outside of the curve is most nearly:
- 39 ft
- 23.1 ft
- 30 ft
- 69 ft
Show the answer & worked solution
Answer: A.39 ft
ft. Distractors: applied the factor then ADDED the full base again, ft (over-applies the adjustment, exceeding the key); DIVIDED by (the wrong direction — that would narrow the zone, as on the inside of the curve), 23.1 ft; and FORGOT the curve adjustment, using the tangent value ft. - 2mediumA. Signal timing, clearance intervals & warrantsA pedestrian phase at a marked crosswalk across a four-lane arterial uses a walk interval of WALK s and a walking speed of ft/s across a crosswalk of length ft. With flashing-don't-walk FDW , the total pedestrian crossing interval (WALK + FDW) is most nearly:
- 24.1 s
- 17.1 s
- 31.1 s
- 15.6 s
Show the answer & worked solution
Answer: A.24.1 s
FDW s; PED WALK FDW s. Distractors: reported ONLY the FDW clearance, forgetting to add the WALK interval (17.14 s); sized FDW on HALF the crosswalk length, (15.57 s); and DOUBLE-COUNTED the WALK interval, adding it twice, WALKFDW (31.14 s). - 3mediumA. Equal-tangent parabola geometry & elevationsAn equal-tangent vertical curve (, , ft) on a crest curve over a ridge has its PVC at elevation 845.00 ft. The roadway elevation ft beyond the PVC is most nearly:
- 851 ft
- 839.33 ft
- 849.33 ft
- 847.67 ft
Show the answer & worked solution
Answer: C.849.33 ft
; ft. Distractors: DROPPED the parabolic term, staying on the tangent (851 ft); used instead of , forgetting the (847.67 ft); and used the OUTGOING grade in the linear term instead of (839.33 ft). - 4mediumA. Signs, markings & temporary traffic control (MUTCD)A work zone on a downtown lane realignment has a lateral offset ft at mph. Compute the merging-taper length ( for mph, for mph), then find the shifting-taper length (). The required taper is most nearly:
- 360 ft
- 60 ft
- 90 ft
- 180 ft
Show the answer & worked solution
Answer: C.90 ft
ft; shifting taper ft. Distractors: reported the FULL merging ft (forgot the fraction); used the OTHER fraction (60 ft, swapping the 0.5L / ⅓L rules); and applied the WRONG speed-regime formula for , ft. - 5mediumA. Uninterrupted flow, capacity & level of serviceOn an urban freeway in the peak direction, the peak-direction hourly volume is veh/h over lanes, with PHF , a heavy-vehicle factor , and a driver-population factor . The demand flow rate per lane is most nearly:
- 1656 pc/h/ln
- 1681 pc/h/ln
- 5480 pc/h/ln
- 1827 pc/h/ln
Show the answer & worked solution
Answer: D.1827 pc/h/ln
pc/h/ln. Distractors: MULTIPLIED by instead of dividing (1656 — wrong direction, since should raise ); FORGOT to divide by , giving a total rate not a per-lane rate (5480); and OMITTED the PHF, leaving an hourly rather than a peak-15-min rate (1681). - 6mediumA. Soil properties, classification, CBR & compactionField density testing on a roadway subgrade lift gives a dry unit weight of pcf; the standard Proctor maximum is pcf and the specification requires 95% relative compaction. The relative compaction achieved is most nearly:
- 90.7%
- 105%
- 95.5%
- 94.5%
Show the answer & worked solution
Answer: C.95.5%
(PASSES the 95% spec). Distractors: INVERTED the ratio, (always >100%, a false pass); subtracted the pcf gap from 100 as if it were a percent, ; and multiplied the ratio by the spec 95 instead of by 100, 90.7%. - 7mediumA. Circular curve geometry & stationingA simple circular curve has radius ft and central angle on a divided-highway curve. The length of the curve (arc PC to PT) is most nearly:
- 293.2 ft
- 33600 ft
- 586.4 ft
- 580.6 ft
Show the answer & worked solution
Answer: C.586.4 ft
ft. Distractors: FORGOT the degree→radian factor, ; reported the LONG CHORD ft (a straight line, shorter than the arc) instead of the arc; and HALVED as if for a tangent term, ft. - 8mediumA. Quantity/cost estimating & engineering economicsRoutine corridor maintenance costs $45,000 per year for 20 years. At i = 5% per year, the present worth of this maintenance stream is most nearly:
- $1,487,968
- $560,799
- $119,398
- $900,000
Show the answer & worked solution
Answer: B.$560,799
; . Distractors: summed with NO discounting ($900,000); used the factor, getting the FUTURE worth of the series instead of the present ($1,487,968); and grabbed the factor, compounding a single payment forward instead of discounting the series ($119,398). - 9mediumA. Highway hydrology & runoffA fully-paved interchange ramp catchment has a runoff coefficient and a drainage area acres. The design rainfall intensity is in/hr. By the rational method (, in cfs), the peak discharge is most nearly:
- 29.6 cfs
- 21.4 cfs
- 18.2 cfs
- 25.2 cfs
Show the answer & worked solution
Answer: B.21.4 cfs
cfs. Distractors: OMITTED (used ), cfs; DIVIDED by instead of multiplying, cfs; and APPLIED twice (squared it), cfs. - 10mediumA. Intersection sight distance & roundabout geometryA stopped driver making a left turn has 650 ft of clear sight distance along a major road posted at mph (required time gap s). Using , the time gap the available sight distance actually provides is most nearly:
- 14.4 s
- 8.84 s
- 10.3 s
- 9.83 s
Show the answer & worked solution
Answer: D.9.83 s
s, which is ≥ the required 7.5 s (so the gap is adequate). Distractors: DROPPED the factor (14.44 s); ROUNDED the factor down to (10.32 s); and mis-read the major-road speed mph too high, using mph (8.84 s).
That was ten. There are thousands.
The full PE Civil: Transportation bank covers every knowledge area at this depth, with timed mock exams that mirror the real 80-question paper and an AI tutor grounded in the PE Civil Reference Handbook + AASHTO (Green Book, HCM, MUTCD, HSM) — so it can't confidently feed you a wrong answer.
Studying for a different exam? See free practice problems for all 11 exams, or read our FE & PE study guides.
These are the same free sample questions available to anyone with an account — the paid bank is separate. Independent study resource; not affiliated with, endorsed by, or sponsored by NCEES.