Raw wastewater passes through primary settling tanks and then an activated-sludge process, and the discharge permit limits the final effluent to BOD. The primary unit removes 35% of the BOD and the secondary unit removes 85% of the BOD reaching it. The highest raw-wastewater BOD (mg/L) the plant can receive and still meet the limit is most nearly: