Construction Engineering
Project administration and delivery methods, construction operations and methods, project controls including earned value and CPM scheduling, estimating, and interpretation of engineering drawings.
4 concepts
Project administration and delivery methods, construction operations and methods, project controls including earned value and CPM scheduling, estimating, and interpretation of engineering drawings.
4 concepts
Choose among design-bid-build, design-build, and CM-at-risk, match the contract type to the risk, and run the paperwork: submittals, RFIs, change orders, progress payments, and OSHA safety.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Convert soil among bank, loose, and compacted states, compute equipment production and truck-fleet matches, and read plan-and-profile drawings and temporary-works requirements.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Build an activity-on-node network, run the forward and backward passes for float and the critical path, then crash and track it with earned value (CPI/SPI).
Earliest an activity can finish; = duration. In day-1 counting use .
An activity cannot start until its latest-finishing predecessor is done.
Latest an activity can start without delaying the project.
Must finish before the earliest-starting successor's late start; last activity seeded at project duration.
Slack before the project finish slips. defines the critical path.
Slack before any successor's early start slips; . The FE Reference Handbook 10.6 prints only total float (Float = LS − ES or LF − EF), not free float.
Dollars per day to compress an activity; crash the cheapest critical activity first.
Budgeted value earned minus actual cost; negative = over budget. =BCWP, =ACWP.
Earned minus planned value; negative = behind schedule. =BCWS (all in dollars).
Dimensionless cost efficiency; means each dollar buys less than a dollar of budgeted work.
Dimensionless schedule efficiency; means work is being earned slower than planned.
Forecast final cost assuming current holds; = budget at completion.
Forward/backward pass, float, and the critical path
Problem. A project has activities A(4 d), B(3 d), C(6 d), D(5 d), E(2 d). A is first. B and C both depend on A. D depends on B. E depends on C and D. Using at the start, find the project duration, the critical path, and the total and free float of activity C.
Crashing to a target duration
Problem. For the same network (critical path A-B-D-E, 14 days; near-critical path A-C-E, 12 days), crash data are: A can crash 1 day at $300/day; B at $500/day; D at $400/day; E at $700/day. Find the least-cost way to deliver in 12 days.
Earned-value status and forecast
Problem. A project has . At the status date the planned value is , the earned value is , and the actual cost is . Compute CV, SV, CPI, SPI, and the estimate at completion. Is the job over or under budget, ahead or behind?
Turn drawings into measured quantities, price them with unit costs and crew productivity, then build the bid from direct cost, overhead, contingency, and profit.
Unlocks with an access pass — one-time payment, no auto-renew. View passes