Project Sitework · Study · PE Civil: Water Resources and Environmental · FE → PE Prep
Project Sitework
13% of exam
Excavation and embankment (cut/fill), horizontal and vertical curve geometry, retaining walls, erosion and sediment control, construction safety, and methods.
9 concepts
A. Excavation and embankment
Earthwork: Cut/Fill, Shrinkage, Swell and the Mass Diagram
Average-end-area volumes, the bank/loose/compacted state changes that govern borrow and haul, and how the mass-haul diagram sets balance points and overhaul.
Earthwork is where a civil project's biggest single cost is won or lost, and where the PE rewards engineers who can keep three different volumes of the ·same· dirt straight. A cubic yard of soil shrinks when you compact it into an embankment and swells when you load it loose into a truck, so 'how much fill do I need' and 'how many truckloads is that' are two different numbers — and confusing them is the classic exam trap. This concept builds the chain from cross-section areas to volumes to the mass-haul diagram, the graphical tool that tells you where to balance cut against fill and when hauling becomes overhaul. It follows the NCEES PE Civil Reference Handbook §2.1 Earthwork Construction and Layout and §2.1.4 Earthwork Balancing and Haul Distances.
Volumes from cross sections: average end area
Field earthwork volumes come from cross sections cut at regular stations (commonly every 100ft
). The workhorse is the average-end-area method: average the two end areas and multiply by the distance between them. It is exact for a prism and slightly ·over·-estimates when the section is changing nonlinearly (the more accurate prismoidal formula uses the midsection area). On the exam, use average end area unless the problem hands you a midsection area or says 'prismoidal.' Treat cut and fill as separate volume tallies — never net them inside a single station because cut and fill soils are paid and moved differently.
V=2A1+A2L
Three states of soil: bank, loose, compacted
The same particles occupy different volumes in the ground (bank measure, BCY), loose in a truck (loose measure, LCY), and compacted in the fill (compacted measure, CCY). What is conserved across all three is dry weight, not volume, so the master relationship is γBVB=γLVL=γCVC. Because loose soil is fluffed up it has the lowest unit weight (γL<γB), and engineered fill is the densest (γC>γB). Anchor every conversion to this weight identity and you can never invert a ratio.
γBVB=γLVL=γCVC
Swell, shrinkage, and load factor
Swell measures the bulking from bank to loose; shrinkage measures the densification from bank to compacted. The PE Civil Reference Handbook defines them on a unit-weight basis: swell(%)=(γB/γL−1)×100 and shrinkage(%)=(1−γB/γC)×100. The load factor LF=γL/γB converts bank volume to loose haul volume (VL=VB/LF), and the shrinkage factor γB/γC converts bank to compacted. The handbook explicitly warns that published definitions vary, so on test day default to its forms and, when in doubt, fall back to weight conservation.
Once volumes are in a common measure you can compare project cut to project fill. If compacted-fill demand exceeds available cut (expressed as compacted equivalent), the deficit is made up from a borrow pit; if cut exceeds fill, the surplus is wasted (exported). The trap is comparing apples to oranges: convert everything to one state — usually compacted (in-place) yards for balancing and loose yards for hauling/trucking. A borrow quantity must be grossed up from compacted demand to bank (to size the pit) and again to loose (to count trucks).
The mass-haul diagram
Plot cumulative earthwork volume up-station, with cut positive and fill negative (after applying shrinkage so cut and fill are in the same measure). Rising segments are net cut, falling segments are net fill. Where the curve crosses its baseline the cumulative volume returns to zero — a ·balance point·: cut between two balance points exactly fills the embankment between them. Peaks and valleys (maxima/minima) line up with ·grade points· on the profile where existing and final grade meet. Any horizontal chord of the curve cuts off equal cut and fill volumes; the horizontal distance from the cut's centroid to the fill's centroid is the average haul distance, and dividing the enclosed area by the curve height gives that haul distance directly.
Freehaul, overhaul, and balancing
Contracts include a ·freehaul· distance: moving material up to that distance is part of the base unit price. Material hauled farther incurs ·overhaul·, priced per station-yard (one cubic yard moved one 100ft station beyond freehaul). The overhaul distance is the centroid-to-centroid haul minus the freehaul distance, and the pay quantity is overhaul volume times overhaul distance. Choosing where to set the horizontal balance lines — and whether to borrow locally rather than overhaul a long way — is the optimization the mass diagram makes visible.
Overhaul=Voh×(dCG-CG−dfreehaul)
Exam strategy
First decide which soil state the question wants and convert everything to it before you do anything else — fill demand in compacted yards, trucking in loose yards, pit size in bank yards. Write the weight-conservation identity γBVB=γLVL=γCVC in the margin so a forgotten swell/shrinkage direction can't bite you. For average end area, keep cut and fill columns separate and watch the units: areas in ft2 times length in ft gives ft3, then divide by 27 for cubic yards. On mass-diagram questions, remember balance points are baseline crossings (zero cumulative volume) and grade points are the peaks/valleys — and that average haul distance = enclosed area ÷ ordinate height.
Key equations
Average end-area volumeV=2A1+A2L
Volume between two cross sections; A1,A2 in ft2, L in ft
Prismoidal volumeV=6L(A1+4Am+A2)
Weight conservation across statesγBVB=γLVL=γCVC
Swell (percent)swell(%)=(γLγB−1)×100
Shrinkage (percent)shrinkage(%)=(1−γCγB)×100
Load factorLF=γBγL,VL=LFVB
Relative compactionRC=γd,maxγd,field×100
Water to add for moistureG=8.33γdV(wdes−wborrow)
Borrow-pit grid square volumeV=4Agrid(a+b+c+d)
Triangular spoil bank volumeV=tanRH2L
Loose spoil pile of length L, height H
Overhaul quantityOverhaul=Voh(dCG-CG−dfh)
Average haul distancedavg=ordinate heightarea under mass curve
Graphical haul distance for a balanced segment of the mass-haul diagram.
Worked examples
Average-end-area cut volume
Problem. Two adjacent cross sections 100ft apart show cut end areas of 120ft2 and 180ft2. Find the cut volume in cubic yards.
Solution. Average the end areas and multiply by the spacing:
V=2A1+A2L=2120+180(100)=150×100=15,000ft3.
V=2120+180(100)=15,000ft3=556cy
Borrow, haul, and truckloads
Problem. An embankment needs 10,000cy of compacted fill. Borrow soil has unit weights γB=105pcf (bank), γL=90pcf
Overhaul payment
Problem. A balanced reach of a mass-haul diagram moves 6,000cy of overhaul material. The centroid of the cut mass is 1,400ft from the centroid of the fill mass, and the contract freehaul distance is 500ft. At an overhaul price of $0.40 per station-yard, find the overhaul cost.
•Mixing soil states: comparing bank cut directly to compacted fill, or counting truckloads off compacted yards. Convert everything to one state first, and gross compacted fill UP to bank/loose for borrow and trucking.
•Inverting swell or shrinkage: loose volume is LARGER than bank (γL<γB), compacted is SMALLER (γC>γB). When unsure, fall back to γBVB=γLVL=γCVC.
•Forgetting the ÷27: areas in ft2 times length in ft give ft3; divide by 27 to report cubic yards.
•Confusing balance points with grade points: balance points are where cumulative volume returns to zero (baseline crossings); grade points are the peaks/valleys where existing and final grade meet.
•Billing the full centroid-to-centroid distance as overhaul. Overhaul distance is the haul MINUS the freehaul distance; the freehaul portion is in the base price.
•Netting cut and fill within one station of average-end-area work. Keep cut and fill as separate tallies — they are different pay items and move differently.
•Using the prismoidal formula when only end areas are given. Default to average end area unless a midsection area is supplied or 'prismoidal' is stated.
References
NCEES PE Civil Reference Handbook — §2.1 Earthwork Construction and Layout
NCEES PE Civil Reference Handbook — §2.1.2 Earthwork Volumes
NCEES PE Civil Reference Handbook — §2.1.4 Earthwork Balancing and Haul Distances
Caterpillar Performance Handbook — swell/shrinkage and load-factor conventions for haul estimating
B. Construction site layout and control
Site Layout, Staking and Construction Control
Horizontal and vertical control, differential leveling with HI/BS/FS bookkeeping, and translating design grades into offset, grade, and slope stakes in the field.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
C. Temporary and permanent soil erosion and sediment control
Erosion and Sediment Control (BMPs and Geosynthetics)
RUSLE soil-loss factors, sediment basin and trap sizing, silt fence and check dams, geosynthetic and riprap channel/slope stabilization, and SWPPP fundamentals.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
D. Impact of construction on adjacent facilities
Impact of Construction on Adjacent Facilities
Excavation-induced settlement and ground movement, dewatering drawdown effects, shoring and underpinning, construction vibration, and monitoring of neighboring structures.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
E. Safety
Construction and Work-Zone Safety (OSHA Trench and Excavation)
OSHA soil types and allowable slopes, protective systems for excavations, the competent-person and access rules, and work-zone traffic-control and exposure basics.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
F. Basic horizontal and vertical curve elements
Horizontal Curve Geometry
Lay out a simple circular curve from R, Δ and the PI: compute T, L, M, E and LC, station the PC and PT, and connect degree of curve to radius.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
Vertical Curve Geometry and Sight Distance
Build elevations on an equal-tangent parabolic curve from the offset equation, locate the high/low point, use the K-value, and size a crest for stopping sight distance.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
G. Retaining walls
Retaining Walls: Sliding, Overturning and Bearing
Check a gravity or cantilever wall against sliding, overturning, and bearing using active/passive earth pressure, base friction, eccentricity, and the trapezoidal base-pressure distribution.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
H. Construction methods
Construction Methods: Dewatering, Cranes, Piles and Trenchless
Choose dewatering and excavation-support systems, check crane lifts against rated capacity, estimate pile capacity from a dynamic driving formula, and place utilities by trenchless methods.
Unlocks with an access pass — one-time payment, no auto-renew. View passes
Pass holders
,
V
in
ft3
(÷27 for cy). Slightly overestimates for nonlinear sections.
More accurate volume using midsection area Am; use when the problem supplies Am or asks for prismoidal.
Master identity. B = bank (in-situ), L = loose (hauled), C = compacted (fill). Dry weight is conserved, volume is not.
Bulking from bank to loose. γL<γB so swell is positive; loose volume VL=VB(γB/γL).
Densification from bank to compacted. γC>γB; compacted volume VC=VB(γB/γC).
Converts bank to loose for trucking; LF<1. Some texts define load factor as the reciprocal — confirm against weight conservation.
Field acceptance ratio of field dry density to laboratory maximum (Proctor); specs commonly require ≥95%.
Gallons of water; γd in lb/ft3, V in ft3, w as decimal moisture content, 8.33lb/gal.
Cut volume of one full grid square from corner cut depths a,b,c,d; Agrid is the plan area of the square.
, angle of repose
R
; base width
B=2H/tanR
.
Pay quantity in station-yards: overhaul volume times the centroid-to-centroid haul beyond the freehaul distance dfh.
Convert to cubic yards:
15,000/27=555.6cy
.
**Answer:
556cy
(bank measure).** Sanity check: a uniform
150ft2
section over
100ft
is
15,000ft3
, and
27ft3=1cy
, so a few hundred cy is the right order of magnitude.
(loose),
γC=122pcf
(compacted). Find the bank volume to excavate, the loose volume to haul, and the number of
12-cy
truckloads.
Solution. Use weight conservation γBVB=γLVL=γCVC.
Bank volume: VB=VCγBγC=10,000105122=11,619cy (bank).
Loose volume: VL=VCγLγC=10,00090122=13,556cy (loose).
Truckloads: 13,556/12=1,130 loads.
**Answers: 11,600BCY, 13,600LCY, 1,130 loads.** Check: shrinkage =(1−105/122)×100=13.9% and swell =(105/90−1)×100=16.7%; loose > bank > compacted in volume, as it must be.