91 key equations from 9 study topics, each with what it is for and where to look it up: the PE Electrical and Computer: Power Reference Handbook section, or the code or textbook when the handbook does not print it. No signup. These are the equations from the free chapters of our PE Electrical and Computer: Power study handbook; the full handbook covers every topic at this depth, with worked examples and the traps that cost points.
91
Equations
9
Study topics
10
Concepts
Circuit Analysis14% of the exam
Three-phase, symmetrical components, per-unit, phasors, 1-φ & DC.
Three-Phase Circuits and Power
Wye and delta relationships, balanced three-phase power, and the √3 conventions that underpin nearly every exam calculation.
- Wye relationships
- Line-line voltage leads line-neutral by 30° (ABC sequence).
- Delta relationships
- Line current lags its phase current by 30° (ABC sequence).
- Three-phase apparent power
- Same total from line or phase quantities.
- Real and reactive power
- θ = load impedance angle = angle between phase voltage and phase current.
- Power triangle
- Lagging = inductive (Q > 0 absorbed).
- Delta→wye impedance
- Balanced loads only.
- Per-phase voltage
- 480 V system → 277 V; 208 V → 120 V; 13.8 kV → 7.97 kV.
Where it lives: NCEES PE Power Reference Handbook §3.1.1 — 3-Phase Circuits · NCEES PE Power Reference Handbook §1.3.1 — Algebra of Complex Numbers · Grainger & Stevenson, Power System Analysis
Read the Circuit Analysis chapterThe Per-Unit System
Normalizing voltage, current, power, and impedance to common bases — the change-of-base formula and why transformers vanish from the math.
- Base current (3-φ)
- S in VA, V in volts → A (or MVA and kV → kA).
- Base impedance
- The kV²/MVA shortcut works directly in those units.
- Per-unit value
- Dimensionless; ×100 gives percent.
- Change of base
- Old voltage base in the numerator; impedance grows with a larger MVA base.
- Per-unit Ohm's law
- No √3 or 3 factors in per-unit.
- Three-phase fault current
- The most common per-unit application; see the fault-analysis concept.
Where it lives: NCEES PE Power Reference Handbook §3.1.3 — Per Unit System · Grainger & Stevenson, Power System Analysis · IEEE Std 399 (Brown Book)
Read the Circuit Analysis chapterRotating Machines7% of the exam
Machine types & applications, motor starting, slip, torque.
Induction Machines: Equivalent Circuit, Power Flow, and Torque
Master slip, the per-phase equivalent circuit, the 1 : s : (1−s) power-flow ladder, and the torque-slip curve behind every induction-motor exam question.
- Slip
- Per-unit. .
- Rotor speed
- Rotor frequency
- Rotor currents at slip frequency; standstill rotor reactance becomes when running.
- Air-gap power
- = stator copper loss.
- Rotor copper loss
- Converted (developed) power
- Power-flow split
- Given any one of the three and the slip, find the other two; and also need the stator and rotational losses.
- Developed torque
- The form is valid even at standstill.
- Shaft output and torque
- = friction and windage; = stray load loss.
- Thevenin voltage
- Per-phase stator reduction seen from the air gap; typically about .
- Torque-slip equation
- All quantities per phase, referred to the stator; in mechanical rad/s. The handbook (§4.2.4) prints the approximate form, with , , in place of , , (assumes ). Use it when a problem gives the raw circuit.
- Slip at maximum torque
- Proportional to rotor resistance — the wound-rotor control handle. The handbook prints the approximate form .
- Breakdown (pull-out) torque
- Independent of . With the handbook's approximate circuit, put , and in place of the Thevenin values.
- Voltage sensitivity
- At any fixed slip. Current at fixed slip scales as .
Where it lives: NCEES PE Power Reference Handbook §4.2 — Induction Machines · NCEES PE Power Reference Handbook §4.2.5 — 3-Phase Induction Motor Power Flow · NEMA MG-1 — Motors and Generators · IEEE Std 112 — Test Procedure for Polyphase Induction Motors and Generators
Read the Rotating Machines chapterElectric Power Devices11% of the exam
Transformers, capacitors, energy storage, PV & wind, testing.
Transformers: Model, Tests, Regulation, and Efficiency
From the ideal transformer to the full equivalent circuit: OC/SC tests, voltage regulation, efficiency, all-day efficiency, taps, and parallel operation.
- Turns ratio
- Impedance refers by a².
- OC test (shunt branch)
- Rated voltage, open secondary; gives core loss.
- SC test (series branch)
- Rated current, shorted secondary; gives copper loss.
- Voltage regulation (approx.)
- θ > 0 lagging; sinθ term negative for leading loads.
- Efficiency
- x = per-unit loading; S = rated VA.
- Maximum-efficiency load
- Copper loss equals core loss at peak efficiency.
- All-day efficiency
- Core loss accrues all 24 h regardless of load.
- Parallel load sharing
- Load divides inversely with per-unit impedance.
Where it lives: NCEES PE Power Reference Handbook §4.3.1 — Transformers · IEEE Std C57.12.00 · IEEE Std C57.12.90 · Chapman, Electric Machinery Fundamentals
Read the Electric Power Devices chapterTransmission & Distribution12% of the exam
Voltage drop & regulation, PF correction, faults, power flow, stability.
Fault Current Analysis
Bolted three-phase faults in per-unit, the MVA method, sequence-network connections for SLG, LL, and DLG faults, and X/R asymmetry.
- 3-φ fault (per-unit)
- Positive-sequence network only.
- Fault MVA
- Series elements: reciprocals add; parallel sources: add.
- SLG fault
- All three networks in series.
- LL fault
- Positive ∥ negative; no zero sequence. The 0.866 ratio assumes Z₁ = Z₂.
- DLG positive-sequence current
- Zero and negative branches in parallel.
- Asymmetry
- Classic ANSI anchors (2.6 peak at X/R = 17; about 2.7 peak and 1.6 total rms at X/R ≈ 25), not upper bounds: both keep rising with X/R toward 2√2 ≈ 2.83 and √3 ≈ 1.73, so use the exact e−ωtR/X expression when X/R is given.
- Utility source impedance
- On the study base, from the utility's available fault MVA.
Where it lives: NCEES PE Power Reference Handbook §5.1.5 — Fault Current Analysis · IEEE Std 141 / 399 (Red/Brown Books) · IEEE Std C37.010 · Blackburn & Domin, Protective Relaying
Read the Transmission & Distribution chapterProtection15% of the exam
Overcurrent, protective relaying, fuses/breakers/reclosers, coordination.
Overcurrent Protection: 50/51 Settings, Inverse Curves, and CT Selection
Set 50/51 pickup and time dial with the IEEE C37.112 curve family, choose CT ratios that will not saturate, and apply residual ground elements.
- IEEE inverse-time operating equation
- Operating time in seconds. = time-dial setting, = multiple of pickup, , , = curve constants per IEEE C37.112.
- Multiple of pickup
- Dimensionless; must exceed 1 for the element to operate. Use fault and pickup on the same side (both primary A or both secondary A).
- Moderately inverse (IEEE)
- Flattest IEEE shape; time changes least with current. Constants from IEEE C37.112 Table 1.
- Very inverse (IEEE)
- Standard choice where fault current falls off along the zone.
- Extremely inverse (IEEE)
- Steepest IEEE shape; best match to fuse melting curves and inrush/cold-load tolerance.
- IEC 60255 curve family
- Standard inverse: , . Very inverse: , . Extremely inverse: , . = time multiplier setting (not interchangeable with IEEE ).
- Primary pickup from tap
- Tap in secondary amps; = CT turns ratio (e.g., 600:5 gives ).
- Reset (disk-emulation) time
- C37.112 reset characteristic that emulates the electromechanical disk's reset (its return travel after current falls below pickup), so a numerical relay coordinates with disk relays on repeated or reclosed faults; is the curve-family reset constant (4.85 moderately, 21.6 very, 29.1 extremely inverse).
- C-class terminal voltage
- A C400 CT delivers into the standard burden = with error.
- CT saturation voltage check
- Symmetrical requirement; multiply by to cover full DC offset. Compare against the C-class voltage.
- Instantaneous setting rule
- Keeps the 50 from overreaching the next downstream bus; on transformer primaries also require (inrush).
- Residual (ground) current
- Phasor sum measured by a 51N in the wye-CT residual; zero for balanced conditions.
Where it lives: NCEES PE Power Reference Handbook §3.1.6 — Single-Line Diagrams · IEEE Std C37.112-2018 — Inverse-Time Characteristic Equations for Overcurrent Relays · IEEE Std C57.13 / C37.110 — Instrument Transformers and CT Application · IEEE Std 242 (Buff Book) — Protection and Coordination of Industrial and Commercial Power Systems · NEC 2020 Art. 240 — Overcurrent Protection
Read the Protection chapterPower Electronics & Controls7% of the exam
Converters, inverter-based resources, VFDs, relays & ladder logic.
Rectifiers and Power Semiconductor Devices
Convert AC to DC: diode and SCR behavior, half-wave, full-wave, and six-pulse outputs, firing-angle control, ripple, and the harmonics rectifiers inject.
- Half-wave average output
- = peak (not RMS) input voltage in volts; single diode, resistive load.
- Half-wave RMS output
- RMS of the half-wave rectified sine; ripple at line frequency .
- Full-wave average output
- Bridge or center-tap; here is the RMS input voltage.
- Full-wave RMS output
- Same RMS as the input sine wave; ripple at (120 Hz on a 60 Hz system).
- Controlled half-wave (SCR)
- = firing (delay) angle in degrees or radians, measured from the natural conduction point; resistive load (the handbook's case — an inductive load keeps the SCR conducting past and lowers the average).
- Controlled full-wave, continuous current
- Single-phase full converter with continuous load current.
- Six-pulse bridge average output
- = RMS line-to-line voltage in volts; diode (uncontrolled) bridge.
- Controlled six-pulse bridge
- Continuous current; goes negative for (line-commutated inverter region).
- Three-pulse (3-phase half-wave) average
- = peak line-to-neutral voltage; = RMS line-to-neutral voltage.
- Form factor and ripple factor
- RF benchmarks: half-wave 1.21, single-phase full-wave 0.483, six-pulse about 0.04.
- Ripple frequency
- = pulse number (1, 2, 6, 12), = line frequency in Hz.
- Characteristic harmonics
- = pulse number, ; six-pulse gives
Where it lives: NCEES PE Power Reference Handbook §3.2.2 — Power Supplies and Converters · IEEE Std 519-2014 — Harmonic Control in Electric Power Systems · NCEES PE Power Reference Handbook §5.1.4 — Power Quality
Read the Power Electronics & Controls chapterMeasurement & Instrumentation9% of the exam
Instrument transformers & metering, insulation & ground testing.
Three-Phase Power Measurement and the Two-Wattmeter Method
Blondel's theorem, the 1-, 2-, and 3-wattmeter methods, two-wattmeter math and sign rules below 0.5 PF, and kWh/demand metering with CT/VT multipliers.
- Wattmeter response
- = angle between the potential-coil voltage and current-coil current. Polarity (±) terminals set the sign.
- Blondel's theorem
- Minimum wattmeter elements for exact total power, balanced or unbalanced. 4-wire → 3; 3-wire → 2.
- Two-wattmeter readings (balanced, ABC sequence)
- = load impedance angle (positive lagging). for lagging PF with this labeling.
- Total real power
- Algebraic sum — include the sign of a negative reading. Exact even for unbalanced 3-wire loads.
- Reactive power from the readings
- Balanced loads only. Positive = lagging (absorbing vars) with the labeling above.
- Power-factor angle
- Balanced loads only; then .
- Single wattmeter, balanced four-wire
- One element reading line-to-neutral voltage and line current of the same phase.
- Power from disk revolutions
- = watthour constant (Wh per revolution), = revolutions, in seconds; in watts at the meter.
- Transformer factor (meter multiplier)
- Multiply every meter-side reading (kWh, kW, disk-derived power) by TF to get primary values.
- Primary watthour constant
- Watthours of primary energy per disk revolution on a transformer-rated installation.
- Block interval demand
- in kWh over a -minute demand interval gives demand in kW (15-min interval → multiply interval kWh by 4).
Where it lives: NCEES PE Power Reference Handbook §2.1 — Measurement and Instrumentation · NCEES PE Power Reference Handbook §3.1.1 — Three-Phase Circuits · ANSI C12.1 — Code for Electricity Metering
Read the Measurement & Instrumentation chapterElectrical Safety14% of the exam
Wiring methods, hazardous locations, special occupancies, shock & burns.
Conductor Sizing, Derating, and OCPD Selection
Size conductors from Table 310.16 with ambient and bundling derating, respect 110.14(C) terminal limits, apply the 125% rule, and pick the OCPD per 240.4/240.6.
- Continuous-load minimum rating
- Minimum conductor table ampacity (at the termination column) and minimum OCPD rating. NEC 210.19(A), 210.20(A), 215.2, 215.3.
- Corrected (derated) ampacity
- from the conductor's insulation column of Table 310.16; must satisfy (100% of actual load).
- Ambient temperature correction factor
- = conductor insulation rating (°C), = ambient (°C). Table 310.15(B)(1) (NEC 2020) is this formula evaluated at the upper temperature of each band.
- Bundling adjustment factor
- Table 310.15(C)(1). CCC = current-carrying conductors in one raceway or cable; EGC never counts.
- Required table ampacity under derating
- Work the derating backward to pick a conductor size directly.
- 10-ft tap minimum ampacity (leaving enclosure)
- NEC 240.21(B)(1); tap must also carry the calculated load and match the terminating device rating.
- 25-ft tap minimum ampacity
- NEC 240.21(B)(2); must terminate in a single OCPD rated no more than the tap ampacity.
Where it lives: NFPA 70-2020 (NEC) Table 310.16, 310.15(B)(1), 310.15(C)(1) · NFPA 70-2020 (NEC) 110.14(C) · NFPA 70-2020 (NEC) 210.19, 210.20, 215.2, 215.3 · NFPA 70-2020 (NEC) 240.4, 240.6, 240.21(B) · NCEES PE Electrical and Computer: Power exam specification (October 2025) — supplied codes and standards
Read the Electrical Safety chapterGeneral Applications11% of the exam
Lightning & surge protection, illumination, demand, grounding.
Demand Calculations and Energy Management
Demand, load, diversity, and coincidence factors; billing demand and rate structures; load profiles and conservation economics.
- Demand factor
- Basis of NEC Art. 220 feeder/service demand tables.
- Load factor
- T = hours in the period (730/month, 8760/yr).
- Diversity factor
- Coincidence factor = 1/Fdiv ≤ 1.
- System peak from parts
- Transformer/feeder sizing with diversity.
- Average demand
- The flat-line equivalent of the load profile.
- Ratchet demand
- k = ratchet percentage, e.g. 0.8.
- Simple payback
- Screening metric for demand-side efficiency comparisons.
Where it lives: NCEES PE Power Reference Handbook §2.2.4 — Demand Calculations / §2.2.5 — Energy Management · NEC 2020 Article 220 · IEEE Std 141 (Red Book)
Read the General Applications chapterNow use them on real questions
Ten free PE Electrical and Computer: Power questions with full worked solutions and figures where needed, no account required. Then the full bank, timed mock exams and the complete study handbook when you are ready.
Many equations follow the PE Electrical and Computer: Power Reference Handbook as NCEES prints it; the rest come from the code, design standard or textbook named in their “Where it lives” line or note. The on-screen reference NCEES supplies on exam day is the copy that counts, so check the edition for your sitting. Independent study resource; not affiliated with, endorsed by, or sponsored by NCEES.